Holdenville School Board Receives Positive Audit Report
Body
The Holdenville Board of Education approved a pay application for bond issue in the amount of $48,459.95 during their January 11 regular monthly meeting. Superintendent Randy Davenport explained that they have finished construction of the steel structure and framing for the all-purpose building at Reed Elementary. There was an inspection earlier that day before they begin adding sheet rock to the inside. They also expect to begin on the plumbing during this time, which should take about a week. This will be followed by the flooring, which should take approximately a week, followed by the heat and air installation. Although they are behind on pouring cement, they are still planning to have the project completed in March. Voters approved this bond issue on September 9, 2019.